01 / Epoch AI / Colossus I
Site capacity, hardware, modeled capital and selected buildout milestones. Adapted under CC BY 4.0. Capital is expressed in constant 2025 dollars. View source
Site capital, installed hardware and Anthropic’s compute-services agreement.
Site aerial · October 8, 2021 · before AI conversion
USDA NAIP / USGS The National Map · Public domain
Riverport campus. Capital figures are modeled estimates in constant 2025 dollars, including compute equipment and facility infrastructure.¹
¹ Epoch AI estimates. $12.9B ÷ 340 IT MW = $37.9M/IT MW. Selected capital snapshots are not cash outlays. Component cost allocation is not established. Source and method ↗
SpaceX’s original May 2026 package supplies Anthropic with compute across both facilities. The service fee covers GPUs, CPUs, storage and networking.²
The GPU count is approximate. This is a service-package blend across unspecified GPU generations, rather than a chip-only rental price.
² SEC-filed disclosure. Fee annualization equals $15B; it is not guaranteed revenue or realized spending. Site-specific pricing is undisclosed.
Per-MW pricing depends on the assumed allocation and power density of the contracted GPUs. These scenarios do not establish a site tariff or a verified price range.
Base scenario: the residual GPUs use the average density of Epoch’s Colossus II Tulane Road inventory. The contracted site and GPU mix are unresolved.
All modeled Colossus I capacity is assigned to Anthropic in this calculation. The residual allocation and its average power density are assumptions.³
$15B ÷ 300 MW = $50M combines the portfolio fee with a Colossus-I-only capacity figure.
Reuters reported a larger xAI compute relationship in Anthropic’s confidential IPO prospectus, largely cancellable with 90 days’ notice.
Matching GPU counts, MW allocations and payment schedules were not reported. The report does not establish an updated unit price.⁴
Site capacity, hardware, modeled capital and selected buildout milestones. Adapted under CC BY 4.0. Capital is expressed in constant 2025 dollars. View source
Original portfolio package: approximately 325,000 GPUs and a $1.25B monthly full-rate fee through May 2029. The package includes supporting infrastructure and permits termination after the initial three-month period on 90 days’ notice. View source
The base scenario uses 946 IT MW / 440,000 GPUs for the residual allocation. The Colossus I sensitivity uses 340 MW / 230,000 GPUs, producing 480.43 modeled portfolio MW and $31.2M/IT MW-year. The two cases are alternative assumptions, not verified bounds. View source
The report describes up to $84.5B of xAI-related spending through 2029. Reuters’ reporting was independently checked; the confidential prospectus was not inspected. Original-package calculations are not a valuation of this later relationship. View source
Anthropic confirms access to GPU capacity in both Colossus 1 and Colossus 2. Its earlier May 6 announcement described Colossus I access. View source
Historical aerial photography is public-domain USDA NAIP / USGS imagery. It predates AI conversion and is not evidence of current installed equipment. Research snapshot: October 19, 2026.