80 IT MW modeledNewest AI-building estimate; delivery remains unconfirmed. Legacy-campus operation does not verify this AI phase. Source
Company-wide CapEx, including finance-lease principal; AI spending is not separately disclosed. H1 actual combines Q1 ($19.84B) and Q2 ($31.08B). H2 is full-year guidance less H1 actual, rather than separate management guidance.
Identified lifetime Meta responsibility. Allocations combine sourced plans and analyst models on their original dollar bases.³
Lifetime responsibility does not establish annual cash outlays. Project-level payment schedules are needed to reconcile annual CapEx.
Hyperion’s $28.4B Meta share includes a $5.4B modeled JV share and a $23B analyst residual.
³ Missing allocation amounts remain unknown. Fifteen allocated records sit within twenty tracked relationships; these are not necessarily twenty separately owned physical campuses.
Q2 CapEx of $31.08B and full-year company guidance of $130–145B, including finance-lease principal. View source
Q1 CapEx of $19.84B on the matching accounting basis. View source
2025 annual CapEx of $72.22B. The historical series includes 2024 $39.23B and 2023 $28.10B on the same company CapEx basis. View source
Earlier annual company CapEx observations and their comparative disclosures. View source
Capacity schedules were reviewed on October 19, 2026 for the same twenty project relationships. Capital allocations retain their October 17 snapshot. Annual capacity totals and the full project schedule table appear in the compute-capacity section. View source
133 IT MW for two AI buildings, externally modeled; May 2 satellite observation supports assessed operation. Further campus expansion is unquantified and excluded. Adapted from Epoch AI under CC BY 4.0. View source
September 8 reporting places opening in late 2026 or early 2027. We assume the full original two-hall Epoch model (178 IT MW) is available by end 2027. Low timing confidence; not a company deadline or confirmed commissioning. Capacity model: https://epoch.ai/data/ai-data-centers/directory/meta-rosemount . View source
80 IT MW modeled for the newest AI building. Its August operating date follows a forecast from May imagery; no subsequent commissioning confirmation was found. Excluded from dated totals, retained as unresolved delivery. View source
168 MW announced for delivery within two years of June 2026. The primary disclosure does not define IT versus facility power. No site-specific conversion is established; excluded from IT totals. Wider Reliance campus and renewable generation are separate. View source
Company CapEx, project capital responsibility and capacity estimates cover different scopes. Lifetime allocations cannot be subtracted from annual spending to establish unallocated cash. Capital snapshot: October 17, 2026. Capacity schedules reviewed October 19, 2026.